DEMO-FC-001 · Demo District Engineering Office 1
Flood-control channel rehabilitation, Sitio Malinaw
Desilting and concrete lining of 1.2 km drainage channel with two outfall structures.
Evidence chain
Approved budget
₱100,000,000
Contract value
₱98,400,000
Contractor
Agos Builders Corp. (demo)
Schedule
2026-02-02 → 2026-12-18
Site verification
Latest inspection geotag is 2.4 km from the approved site. Independent site visit needed before any conclusion.
Progress
Gap of 8 points between reported and inspected progress.
Risk indicators
- High Inspection location is 2.4 km from the approved site
Tolerance is 250 m. No approved change order moving the site is on file. Needs an independent site visit before any conclusion.
Evidence timeline
Project registered · 2025-11-04
Public summaryProject registered with approved budget and site coordinates.
Planning Section, Demo DEO 1 · source: DIME (simulated)
digest computing…not yet anchoredProcurement notice · 2025-11-20
Public summaryInvitation to bid posted; 4 bidders.
Bids and Awards Committee, Demo DEO 1 · source: PhilGEPS (simulated)
digest computing…not yet anchoredContract awarded · 2026-01-15
Public summaryContract awarded to Agos Builders Corp. (demo).
Head of Procuring Entity, Demo DEO 1 · source: PhilGEPS (simulated)
digest computing…not yet anchoredBaseline survey · 2026-01-28
AgencyPre-construction survey at approved coordinates; existing unlined channel.
Survey Team, Demo DEO 1 · source: Field inspection app (simulated)
digest computing…not yet anchoredSite inspection · 2026-07-10
AgencyMilestone 2 inspection. Geotag 2.3 km from approved site; no location change order on file.
Project Engineer, Demo DEO 1 · source: Field inspection app (simulated)
digest computing…not yet anchoredProgress reported · 2026-07-14
Public summaryContractor reports 72% accomplishment.
Contractor progress report · source: Agency project system (simulated)
digest computing…not yet anchoredInvoice submitted · 2026-07-20
AgencyProgress billing no. 2.
Agos Builders Corp. (demo) · source: Agency project system (simulated)
digest computing…not yet anchoredPHP payment instruction · 2026-08-03
AgencyPayment instruction issued in PHP.
Accounting Section, Demo DEO 1 · source: Government financial system (simulated)
digest computing…not yet anchoredBank confirmation · 2026-08-05
Public summaryCredit confirmed, amount and reference match.
Servicing bank (simulated) · source: Bank reconciliation simulator
digest computing…not yet anchored
PHP payments
| Voucher / invoice | Instruction | Bank confirmation | Status |
|---|---|---|---|
| DV-DEMO-2207 AB-INV-1042 | ₱31,500,000 2026-08-03 | ₱31,500,000 BNK-DEMO-88321 · 2026-08-05 | Reconciled |